No one may prospect for minerals or carry on mining or processing operations except under a mineral right (Mining Act, Cap. 123 R.E. 2023, s. 7). Section 8 lists the rights: prospecting licences (including gemstone prospecting licences), special mining licences (SML) for large-scale mines, mining licences (ML) for medium-scale mines, primary mining licences for small-scale miners, and processing, smelting and refining licences. A prospecting licence gives an exclusive right to explore for up to four years, renewable twice for up to two years each (s. 42). Its holder is an “entitled applicant” for an SML or ML over the area (s. 49). An SML is granted by the Mining Commission only after Cabinet approval and lasts for the estimated life of the ore body (ss. 52 and 53); an ML is granted by the Commission and renewable for periods of up to ten years (s. 63). Rights are transferable only with consent (s. 10), and may be suspended or cancelled for default after a 30-day default notice (s. 74).
On this page 9 sections
- What mineral rights exist?
- Who may hold a mineral right?
- How does a prospecting licence work?
- How is a special mining licence obtained?
- How does a mining licence differ?
- When can rights be transferred, suspended or cancelled?
- Exam focus: what do examiners ask here?
- Practice question: the expiring prospecting licence
- Key takeaways
What mineral rights exist?
| Right | Division of Part IV | Purpose | Granted by |
|---|---|---|---|
| Prospecting licence and gemstone prospecting licence | A (ss. 38 to 46) | Exploration | Mining Commission |
| Special mining licence | B (ss. 49 to 58) | Large-scale mining | Commission after Cabinet approval |
| Mining licence | B (ss. 59 to 63) | Medium-scale mining | Mining Commission |
| Primary mining licence | C (ss. 64 to 68) | Small-scale and artisanal mining by Tanzanians | Mining Commission |
| Primary processing, processing, smelting and refining licences | D (ss. 69 to 72) | Treatment and refining of minerals | Mining Commission |
The Mineral Rights Regulations draw the line between an SML and an ML by the size of the investment: large-scale operations with a capital investment of at least US$100 million require an SML. Retention licences, which allowed holders to keep a discovered deposit without developing it, were abolished in 2017 (the former provisions are now the repealed ss. 47 and 48), and existing retention licences reverted to the Government. Primary mining licences are covered in Mineral Rights II: Primary Mining Licences and Artisanal and Small-Scale Mining.
Applications are made through the Mining Cadastre, which receives and processes applications, administers rights and maintains public cadastral maps and registers (s. 36); applications are now filed online. Competing applications are ranked by priority (s. 15), and the Minister may invite tenders for vacant areas (s. 16).
Who may hold a mineral right?
Section 9(1) disqualifies:
- individuals under 18; non-citizens not ordinarily resident in Tanzania for four years; undischarged bankrupts; and persons convicted within the previous ten years of an offence involving dishonesty or a mining offence with imprisonment or a fine above TZS 20 million;
- companies without a physical and postal address in Tanzania; companies not incorporated under the Companies Act, Cap. 212 where they intend to mine under a mining licence; companies in liquidation; and companies whose directors or shareholders are disqualified.
Primary mining licences are reserved for Tanzanians (s. 9(2)), and mining licences for gemstones may be granted only to Tanzanians (s. 9(5)), subject to exceptions approved by the Minister after consultation with the Commission (s. 9(6)).
How does a prospecting licence work?
- Application (s. 38) with a prospecting programme and proposed expenditure, or by tender for designated areas (s. 39).
- Minimum expenditure (s. 40): the holder must spend a prescribed amount per square kilometre each year, with different amounts for different mineral groups.
- Duration (s. 42): an initial period of up to four years, a first renewal of up to two years and a second renewal of up to two years; it cannot be renewed after the second renewal, and the area then reverts to the Government. Renewal applications must be made within one month before expiry (s. 42(2)). A company wishing to prospect in an area licensed to a local mining company must conclude an arrangement with it after Cabinet approval (s. 42(1)(f)).
- Rights (s. 45): the exclusive right to prospect for the minerals covered, to enter the area, erect camps and take samples, subject to restrictions on entry (s. 120).
- Obligations (s. 46): start within three months, notify any discovery of potential commercial value, follow the programme and meet the expenditure requirement. A holder who fails is in default; a false statement about these obligations is an offence.
How is a special mining licence obtained?
- The holder of a prospecting licence is an entitled applicant for an SML or ML over its prospecting area (s. 49(1)).
- The application must state the period sought and the known deposits and reserves, and include the mining programme with forecast capital investment and recovery rates, a relocation, resettlement and compensation plan under the Land Act, an environmental certificate under the Environmental Management Act, infrastructure requirements, a procurement plan for local goods and services, an employment, training and succession plan, an integrity pledge and a local content plan (s. 51(3)).
- The Commission checks compliance and sends the application to the Minister for tabling before the Cabinet (s. 52(1)).
- After Cabinet approval, the Commission grants the licence if there are sufficient reserves to justify commercial exploitation, the area is no larger than reasonably required, and the programme, finances and technical resources are adequate (s. 52(2)).
- The licence lasts for the estimated life of the ore body indicated in the feasibility study, or the shorter period requested (s. 53), and may be renewed on application made at least one year before expiry (s. 55).
The holder has the exclusive right to mine the specified minerals in the area and to erect plant and buildings (s. 56). It must start mining within 18 months, mine in substantial compliance with its programme and environmental management plan, employ and train Tanzanians and implement a succession plan for expatriates, demarcate the area, prepare and update mine closure plans and implement relocation and compensation in accordance with the Land Act (s. 57). The Government is entitled to at least a 16 per cent free carried interest in the company (s. 11); see The Mining Fiscal Regime: Royalties, State Participation, Taxes and Levies.
How does a mining licence differ?
A mining licence follows the same pattern for medium-scale operations. The application includes a feasibility study and mining programme (s. 59). The Commission must grant a properly made application unless, for example, the applicant is disqualified, the area is excessive, the training programme is unsatisfactory, the applicant is in default on another right, or the area is subject to another right or reserved for primary licences (s. 60). The holder has the exclusive right to mine (s. 61) and must start within 18 months, protect the environment under the Environmental Management Act, implement resettlement and compensation, and employ and train Tanzanians (s. 62). Renewal applications must be made at least six months before expiry, with a tax clearance certificate, and renewals are for up to ten years (s. 63).
When can rights be transferred, suspended or cancelled?
| Issue | Rule | Section |
|---|---|---|
| Assignment | A mineral right may be assigned, but an SML or ML may not be assigned without the written consent of the licensing authority, except to approved affiliates or to banks as security | s. 10 |
| Change of control | A company holding a mineral right may not register share transfers or agreements giving a person control (50 per cent or more of shares or power to appoint half the board) without consent | s. 158 |
| Suspension or cancellation | For material breach of the Act, licence conditions, lawful directions or the development agreement, after a default notice and 30 days to remedy (or to offer compensation where the default cannot be remedied) | s. 74 |
| Challenge | An aggrieved holder may apply to the High Court for judicial review within 60 days | s. 76 |
| Insufficient production | An ML may be terminated where, for at least three years, production is below 50 per cent of the feasibility study estimate | s. 83 |
| Surrender and abandonment | Procedures for surrendering land and leaving it safe | ss. 73 and 75 |
Exam focus: what do examiners ask here?
- Discuss the types of mineral rights under the Mining Act and the requirements for each.
- Explain the procedure for grant of a special mining licence and the role of the Cabinet.
- Discuss the grounds and procedure for suspension and cancellation of mineral rights.
- Explain the legal effect of abolishing retention licences in 2017.
Practice question: the expiring prospecting licence
Question: Ruvu Resources Ltd, a Tanzanian subsidiary of a foreign company, has held a prospecting licence for copper since 2019 and renewed it twice. It has found a deposit requiring an investment of US$250 million but its feasibility study is not complete. Its parent also plans to sell 60 per cent of Ruvu’s shares to a Chinese investor. Advise Ruvu.
- The licence cannot be renewed a third time (s. 42(1)(d)); the area will revert to the Government unless Ruvu applies for a mining right before expiry.
- As an entitled applicant (s. 49), Ruvu should apply for an SML because of the size of the investment, with a complete feasibility study and the documents in s. 51; the application needs Cabinet approval (s. 52).
- Ruvu cannot hold the deposit without developing it, since retention licences no longer exist.
- The share sale gives the investor control and needs prior consent under s. 158; transfer of the right itself needs consent under s. 10(2).
- Ruvu should plan for the Government’s free carried interest (s. 11) and its local content and CSR obligations.
Key takeaways
- Mining requires a mineral right (s. 7); the types are listed in s. 8.
- Prospecting licences last up to four years plus two renewals of up to two years each (s. 42).
- SMLs need Cabinet approval and last for the life of the ore body (ss. 52 and 53); MLs are renewable for up to ten years (s. 63).
- Retention licences were abolished in 2017.
- Transfers and changes of control need consent (ss. 10 and 158); cancellation needs a default notice and 30 days to remedy (s. 74), with judicial review within 60 days (s. 76).
Key Statutes and Cases on Mineral Rights I: Prospecting, Mining and Special Mining Licences
Statutes
- Mining Act, Cap. 123 R.E. 2023s. 7 authority required; s. 8 types of rights; s. 9 disqualifications; s. 10 transfer; ss. 15 and 16 priority and tender; s. 36 Mining Cadastre; ss. 38 to 46 prospecting licence; ss. 49 to 58 special mining licence; ss. 59 to 63 mining licence; s. 74 suspension and cancellation; s. 76 judicial review; s. 83 insufficient production; s. 158 change of control
- Mining (Mineral Rights) RegulationsThresholds, forms and procedures (as amended in 2025)
Test yourself
Mineral Rights I: Prospecting, Mining and Special Mining Licences Quiz
10 questions · instant feedback