Environmental Law notes · Topic 4 of 8

Environmental Impact Assessment and Strategic Environmental Assessment

The EIA process in Tanzania under section 81 of the Environmental Management Act, Cap. 191 and the EIA and Audit Regulations (GN 349 of 2005, amended by GN 474 of 2018): which projects need an EIA, registration and screening, scoping and terms of reference, the study and public participation, NEMC review within 60 days, the Minister's decision and certificate, conditions, environmental audits, and strategic environmental assessment of policies and plans.

  • Isack Kimaro, LL.B, PDLPBy Isack Kimaro, LL.B, PDLP
  • Reviewed
  • 11 min read

In short

Section 81 of the Environmental Management Act, Cap. 191 requires any proponent or developer of a project listed in the EIA Regulations to undertake an environmental impact assessment (EIA) at its own cost before starting the project, and no licensing authority may issue a permit for such a project without an EIA certificate. The process runs through NEMC: registration and screening, scoping and terms of reference, an EIA study with public participation, submission of an environmental impact statement (EIS), review by NEMC within 60 days (s. 87(1)), and the Minister’s decision to approve with conditions or reject. Strategic environmental assessment (SEA) applies the same idea to policies, plans and programmes.

On this page 8 sections
  1. Which projects need an EIA?
  2. What are the steps in the EIA process?
  3. What are the consequences of not doing an EIA?
  4. What is an environmental audit?
  5. What is strategic environmental assessment?
  6. Exam focus
  7. Practice question: the beach hotel
  8. Key takeaways

Which projects need an EIA?

  • Projects listed in the First Schedule to the EIA Regulations, as revised in 2018 into categories: Type A projects (mandatory full EIA, such as large mines, dams, refineries, major roads and large hotels in sensitive areas) and Type B projects (which may need a partial or full assessment after screening). Some small projects are exempt or need only registration.
  • The category depends on the type, size and location of the project, and sensitivity of the area.

What are the steps in the EIA process?

  1. Registration: the developer registers the project with NEMC, submitting an application and project brief.
  2. Screening: NEMC decides whether a full EIA is needed.
  3. Scoping and terms of reference: the key issues are identified with stakeholders; NEMC approves the terms of reference.
  4. EIA study: a registered environmental expert assesses baseline conditions, likely impacts, alternatives and mitigation measures, and prepares an environmental and social management plan.
  5. Public participation: consultation with affected communities and stakeholders; NEMC may hold public hearings.
  6. Submission of the EIS to NEMC.
  7. Review: NEMC reviews the EIS with a cross-sectoral technical advisory committee, usually including a site visit, within 60 days of submission (s. 87(1)).
  8. Decision: NEMC recommends to the Minister, who approves (issuing an EIA certificate with conditions), requires more information, or disapproves.
  9. Monitoring and audit: the developer implements the management plan; NEMC monitors and may require environmental audits.

Key Statutes and Cases on Environmental Impact Assessment and Strategic Environmental Assessment

Statutes

  • Environmental Management Act, Cap. 191Part VI: s. 81 obligation to undertake EIA before commencing listed projects; NEMC review (s. 87(1), within 60 days of submission of the EIS); approval or disapproval; cancellation of licences issued without EIA; appeals; fresh EIA; Part VII strategic environmental assessment
  • Environmental Management (Environmental Impact Assessment and Audit) Regulations, GN 349 of 2005Procedure, project categories, public participation, audits
  • Environmental Management (EIA and Audit) (Amendment) Regulations, GN 474 of 2018Revised project categories (Type A and B) and procedure
  • Environmental Management (Registration and Practice of Environmental Experts) Regulations, GN 267 of 2021Registration of experts

Cases

  • Festo Balegele and 794 Others v Dar es Salaam City Council, Misc. Civil Cause No. 90 of 1991 (HC, 1992)Public authorities must act lawfully when siting polluting activities

Test yourself

Environmental Impact Assessment and Strategic Environmental Assessment Quiz

10 questions · instant feedback · 5 free

Take the quiz

Get the Full Environmental Law Notes, Quizzes and Templates

Read every topic in full, take every quiz and download court-ready templates. Plans start at TSh 5,000 a week with M-Pesa, Airtel Money, Mixx by Yas or Halotel.

Jiunge leo, usome bila kikomo.

Keep reading this topicFrom TSh 5,000 a weekJoin Now